EU projects

INNOVATIVE ECONOMY

EU projects

December 2008

The company has signed an agreement with PARP for co-financing an investment project under Measure 4.4 of the Innovative Economy Operational Program. 

September 2009

The implementation of the first stage of the project has started.

August 2010

The implementation of the first investment stage in the amount of 1.399.242 PLN has been completed and an application for an indirect payment of 458.768 PLN was submitted.

December 2010

Obtaining an indirect payment for the implementation of the first stage of investment in the amount of 458.768 PLN.

January 2011

Completion of the second investment stage in the amount of 1.045.893,50 PLN and submission of an application for an indirect payment in the amount of 418.369,40 PLN.

August 2011

Obtaining an indirect payment for the implementation of the second investment stage in the amount of 418.369,40 PLN.

September 2011

The implementation of three further stages has commenced.

January 2012

An extension of the contract execution time until 05.2013 was obtained.

January 2012

Completion of the third stage of the investment.

April 2012

Obtaining an indirect payment for the implementation of the third stage of the investment in the amount of 127.200 PLN.

August 2012

Completion of the fourth stage of the investment.

December 2012

An indirect payment was obtained for the implementation of stage IV of the investment.

august 2014

The implementation of the fifth stage has been completed.

November 2014

An indirect payment was obtained for the implementation of stage V of the investment.

June 2015

Stages VI and VII have been completed. A final payment application has been submitted.

November 2015

All payments were received and the project was completed.